Combined Application of 4D BIM Schedule and an Immersive Virtual Reality on a Modular Project: UNLV Solar Decathlon Case

Authors

  • Rajarshi Ghimire University of Nevada, Las Vegas
  • Seungtaek Lee University of Nevada, Las Vegas
  • Jin Ouk Choi University of Nevada, Las Vegas
  • Jin-Yeol Lee University of Nevada, Las Vegas
  • Yong-Cheol Lee Louisiana State University

DOI:

https://doi.org/10.29173/ijic236

Keywords:

Off-site construction, Immersive virtual reality, 4D schedule, Solar Decathlon, Industrialized construction

Abstract

The use of a 4D schedule as technological advancement has brought significant improvement to the planning and execution of construction projects, through visualizing step-wise construction progress, following a sequence of pre-planned activities, and finalizing a baseline schedule with necessary changes. Moreover, the application of immersive virtual reality (IVR) to create an interactive 4D BIM schedule of a planned structure has made it possible to create a detailed plan of any construction project. Because of these benefits, the use of 4D schedules and immersive virtual reality in the construction industry has increased, leading to improved planning and execution. However, past studies have given little attention to the applications of such technologies on modular projects. Thus, this research applied a 4D schedule, along with immersive virtual reality, on a modular project, and verified their benefits and effectiveness. The results showed that most of the participants who experienced a 4D BIM schedule, along with immersive virtual reality (4D/IVR), strongly agreed that it is an easy and straightforward way to visualize the project, understand the schedule, and find any errors. Moreover, while fewer than half of the participants scheduled the assembly sequence correctly with conventional schedule and 2D drawings, almost all of them sequenced the assembly successfully with 4D/IVR. Based on the findings, this research concludes that the implementation of a 4D BIM schedule, along with virtual reality technology, can enhance the fabrication and assembly performance of modules.

References

Tatum, C. B., Vanegas, J. A., and Williams, J. M. (1986). Constructability improvement using prefabrication, preassembly, and modularization. Bureau of Engineering Research, University of Texas at Austin, Austin, Texas, USA.

Haas, C. T., O’Connor, J. T., Tucker, R. L., Eickmann, J. A., and Fagerlund, W. R. (2000). Prefabrication and preassembly trends and effects on the construction workforce. Center for Construction Industry Studies, University of Texas at Austin, Austin.

Song, J., Fagerlund, W. R., Haas, C. T., Tatum, C. B., and Vanegas, J. A. (2005). “Considering prework on industrial projects.” Journal of Construction Engineering and Management, 131(6),723-733. https://doi.org/c98ck5

O’Connor, J. T., O’Brien, W. J., and Choi, J. O. (2016). “Industrial project execution planning: Modularization versus stick-built.” Practice Periodical on Structural Design and Construction, 21(1), 04015014. https://doi.org/fqrn

Hu, R., Pan, W., and Bock, T. (2020). “Towards dynamic vertical urbanism. International Journal of Industrialized Construction, 1(1), 34-47. https://doi.org/10.29173/ijic208

Choi, J. O., Chen, X. B., and Kim, T. W. (2019). “Opportunities and challenges of modular methods in dense urban environment.” International Journal of Construction Management, 19(2), 93-105. https://doi.org/10.1080/15623599.2017.1382093

Moon, H., Dawood, N., and Kang, L. (2014). “Development of workspace conflict visualization system using 4D object of work schedule.” Advanced Engineering Informatics, 28(1), 50-65. https://doi.org/10.1016/j.aei.2013.12.001

Kamat, V. R., and Martinez, J. C. (2001). “Visualizing simulated construction operations in 3D.” Journal of Computing in Civil Engineering, 15(4), 329-337. https://doi.org/c2f4m6

Kim, C., Kim, B., and Kim, H. (2013). “4D CAD model updating using image processing-based construction progress monitoring.” Automation in Construction, 35, 44-52. https://doi.org/10.1016/j.autcon.2013.03.005

Trebbe, M., Hartmann, T., and Dorée, A. (2015). “4D CAD models to support the coordination of construction activities between contractors.” Automation in Construction, 49, 83-91. https://doi.org/10.1016/j.autcon.2014.10.002

Heigermoser, D., de Soto, B. G., Abbott, E. L. S., and Chua, D. K. H. (2019). “BIM-based Last Planner System tool for improving construction project management.” Automation in Construction, 104, 246-254. https://doi.org/10.1016/j.autcon.2019.03.019

Hu, Z., and Zhang, J. (2011). “BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 2. Development and site trials.” Automation in Construction, 20(2), 167-180. https://doi.org/10.1016/j.autcon.2010.09.014

Sloot, R. N. F., Heutink, A., and Voordijk, J. T. (2019). “Assessing usefulness of 4D BIM tools in risk mitigation strategies.” Automation in Construction, 106, 102881. https://doi.org/10.1016/j.autcon.2019.102881

Ma, Z., Shen, Q., and Zhang, J. (2005). “Application of 4D for dynamic site layout and management of construction projects.” Automation in Construction, 14(3), 369-381. https://doi.org/10.1016/j.autcon.2004.08.011

Taghaddos, H., Eslami, A., Hermann, U., AbouRizk, S., and Mohamed, Y. (2019). “Auction-based Simulation for Industrial Crane Operations.” Automation in Construction, 104, 107-119. https://doi.org/10.1016/j.autcon.2019.03.015

Kinateder, M., Ronchi, E., Nilsson, D., Kobes, M., Müller, M., Pauli, P., and Mühlberger, A. (2014, September). “Virtual reality for fire evacuation research.” Proceedings, 2014 Federated Conference on Computer Science and Information Systems, Warsaw, Poland, Sept. 7-10, pp. 313-321. https://doi.org/10.15439/2014F94

Rüppel, U., and Schatz, K. (2011). “Designing a BIM-based serious game for fire safety evacuation simulations.” Advanced Engineering Informatics, 25(4), 600-611. https://doi.org/10.1016/j.aei.2011.08.001

Sacks, R., Perlman, A., and Barak, R. (2013). “Construction safety training using immersive virtual reality.” Construction Management and Economics, 31(9), 1005-1017. https://doi.org/10.1080/01446193.2013.828844

Xing, X., Li, H., Li, J., Zhong, B., Luo, H., and Skitmore, M. (2019). “A multicomponent and neurophysiological intervention for the emotional and mental states of high-altitude construction workers.” Automation in Construction, 105. https://doi.org/10.1016/j.autcon.2019.102836

Kumar, S., Hedrick, M., Wiacek, C., and Messner, J. I. (2011). “Developing an experienced-based design review application for healthcare facilities using a 3D game engine.” Journal of Information Technology in Construction (ITcon), 16(6), 85-104.

Al-Adhami, M., Ma, L., and Wu, S. (2018). “Exploring virtual reality in construction, visualization and building performance analysis.” Proceedings, 35th ISARC International Symposium on Automation and Robotics in Construction, Berlin, Germany, July 2018, pp. 969-976. https://doi.org/10.22260/ISARC2018/0135

Wang, H. J., Zhang, J. P., Chau, K. W., and Anson, M. (2004). “4D dynamic management for construction planning and resource utilization.” Automation in Construction, 13(5), 575-589. https://doi.org/10.1016/j.autcon.2004.04.003

Wang, L. (2007). “Using 4D Modeling to advance construction visualization in engineering education.” Unpublished doctoral dissertation, Penn. State University.

O’Connor, J. T., O’Brien, W. J., and Choi, J. O. (2014). “Critical success factors and enablers for optimum and maximum industrial modularization.” Journal of Construction Engineering and Management, 140(6), 04014012. https://doi.org/f54hzk

O’Connor, J. T., O’Brien, W. J., and Choi, J. O. (2015). “Standardization strategy for modular industrial plants.” Journal of Construction Engineering and Management, 141(9), 04015026. https://doi.org/f7n9b3

Choi, J. O., O’Connor, J. T., and Kim, T. W. (2016). “Recipes for cost and schedule successes in industrial modular projects: Qualitative comparative analysis.” Journal of Construction Engineering and Management, 142(10), 04016055. https://doi.org/f85jhx

Innella, F., Arashpour, M., and Bai, Y. (2019). “Lean methodologies and techniques for modular construction: Chronological and critical review.” Journal of Construction Engineering and Management, 145(12), 04019076. https://doi.org/fqrp

Gbadamosi, A. Q., Mahamadu, A. M., Oyedele, L. O., Akinade, O. O., Manu, P., Mahdjoubi, L., and Aigbavboa, C. (2019). “Off-site construction: Developing a BIM-Based optimizer for assembly.” Journal of Cleaner Production, 215, 1180-1190. https://doi.org/10.1016/j.jclepro.2019.01.113

Yu, H., Al-Hussein, M., Al-Jibouri, S., and Telyas, A. (2013). “Lean transformation in a modular building company: A case for implementation.” Journal of Management in Engineering, 29(1), 103-111. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000115

Nahmens, I., and Ikuma, L. H. (2012). “Effects of lean construction on sustainability of modular homebuilding.” Journal of Architectural Engineering, 18(2), 155-163. https://doi.org/d8vz4p

Khodabandelu, A., Choi, J. O., Park, J., Sanei, M. (2020). “Developing a simulation model for lifting a modular house.” Proceedings, Construction Research Congress (CRC) 2020, Tempe, Arizona, USA, March 8–10, pp. 145-152 https://doi.org/10.1061/9780784482865.016

Choi, J. O., O’Connor, J. T., Kwak, Y. H., and Shrestha, B. K. (2019). “Modularization business case analysis model for industrial projects.” Journal of Management in Engineering, 35(3), 04019004. https://doi.org/fqrr

Choi, J. O., Shrestha B.K., Shane, J., Kwak, Y.H. (2020). “Innovative technologies and management approaches for facility design standardization and modularization of capital projects.” Journal of Management in Engineering, 10. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000805

Ghannad, P., Lee, Y.-C., and Choi, J. O. (2020). “Feasibility and implications of the modular construction approach for rapid post-disaster recovery.” International Journal of Industrialized Construction, 1(1), 64-75. https://doi.org/10.29173/ijic220

Rausch, C., Edwards, C., and Haas, C. (2020). “Benchmarking and Improving Dimensional Quality on Modular Construction Projects–A Case Study.” International Journal of Industrialized Construction, 1(1), 2-21. https://doi.org/10.29173/ijic212

Retik, A., Warszawski, A., and Banai, A. (1990). “The use of computer graphics as a scheduling tool.” Building and Environment, 25(2), 133-142. https://doi.org/10.1016/0360-1323(90)90025-M

Chau, K. W., Anson, M., and Zhang, J. P. (2004). “Four-dimensional visualization of construction scheduling and site utilization.” Journal of Construction Engineering and Management, 130(4), 598-606. https://doi.org/fcb4np

Chau, K. W., Anson, M., and Zhang, J. P. (2005). “4D dynamic construction management and visualization software: 1. Development.” Automation in Construction, 14(4), 512-524. https://doi.org/10.1016/j.autcon.2004.11.002

Chau, K. W., Anson, M., and De Saram, D. D. (2005). “4D dynamic construction management and visualization software: 2. Site trial.” Automation in Construction, 14(4), 525-536. https://doi.org/10.1016/j.autcon.2004.11.005

Mahalingam, A., Kashyap, R., and Mahajan, C. (2010). “An evaluation of the applicability of 4D CAD on construction projects.” Automation in Construction, 19(2), 148-159. https://doi.org/10.1016/j.autcon.2009.11.015

Turkan, Y., Bosche, F., Haas, C. T., and Haas, R. (2012). “Automated progress tracking using 4D schedule and 3D sensing technologies.” Automation in Construction, 22, 414-421. https://doi.org/10.1016/j.autcon.2011.10.003

Kim, C., Son, H., and Kim, C. (2013). “Automated construction progress measurement using a 4D building information model and 3D data.” Automation in Construction, 31, 75-82. https://doi.org/10.1016/j.autcon.2012.11.041

olde Scholtenhuis, L. L., Hartmann, T., and Dorée, A. G. (2016). “4D CAD based method for supporting coordination of urban subsurface utility projects.” Automation in Construction, 62, 66-77. https://doi.org/10.1016/j.autcon.2015.10.013

Kassem, M., Dawood, N., and Chavada, R. (2015). “Construction workspace management within an Industry Foundation Class-Compliant 4D tool.” Automation in Construction, 52, 42-58. https://doi.org/10.1016/j.autcon.2015.02.008

Braun, A., and Borrmann, A. (2019). “Combining inverse photogrammetry and BIM for automated labeling of construction site images for machine learning.” Automation in Construction, 106, 102879. https://doi.org/10.1016/j.autcon.2019.102879

Yin, X., Liu, H., Chen, Y., and Al-Hussein, M. (2019). “Building information modelling for off-site construction: review and future directions.” Automation in Construction, 101, 72-91. https://doi.org/10.1016/j.autcon.2019.01.010

Sacks, R., Eastman, C. M., Lee, G., and Orndorff, D. (2005). “A target benchmark of the impact of three-dimensional parametric modeling in precast construction.” PCI Journal, 50(4), 126.

Singh, M. M., Sawhney, A., and Borrmann, A. (2019). “Integrating rules of modular coordination to improve model authoring in BIM.” International Journal of Construction Management, 19(1), 15-31. https://doi.org/10.1080/15623599.2017.1358077

Collins, J. (2016). “Incorporating BIM into Architectural Precast Concrete Fabrication.” Proceedings, 33rd International Symposium on Automation and Robotics in Construction, ISARC, Auburn, USA, July 18-21, pp. 392-402. https://doi.org/10.22260/ISARC2016/0048

Mao, C., Xie, F., Hou, L., Wu, P., Wang, J., and Wang, X. (2016). “Cost analysis for sustainable off-site construction based on a multiple-case study in China.” Habitat International, 57, 215-222. https://doi.org/10.1016/j.habitatint.2016.08.002

Sharma, S., Sawhney, A., and Arif, M. (2017). “Parametric modelling for designing offsite construction.” Procedia Engineering, 196, 1114-1121. https://doi.org/10.1016/j.proeng.2017.08.069

Yuan, Z., Sun, C., and Wang, Y. (2018). “Design for Manufacture and Assembly-oriented parametric design of prefabricated buildings.” Automation in Construction, 88, 13-22. https://doi.org/10.1016/j.autcon.2017.12.021

Barkokebas, B., Zhang, Y., Ritter, C., and Al-Hussein, M. (2017). “Building information modelling and simulation integration for modular construction manufacturing performance improvement.” Proceedings, European Modelling and Simulation Symposium, pp. 409-415.

Alwisy, A., Bu Hamdan, S., Barkokebas, B., Bouferguene, A., and Al-Hussein, M. (2019). “A BIM-based automation of design and drafting for manufacturing of wood panels for modular residential buildings.” International Journal of Construction Management, 19(3), 187-205. https://doi.org/10.1080/15623599.2017.1411458

Wang, Y., and Yuan, Z. (2017). “Research on BIM-based assembly sequence planning of prefabricated buildings.” Proceedings, International Conference on Construction and Real Estate Management, (ICCREM 2017), Guangzhou, China, November 10–12, pp. 10-17. https://doi.org/10.1061/9780784481059.002

Wang, Y., Yuan, Z., and Sun, C. (2018). “Research on assembly sequence planning and optimization of precast concrete buildings.” Journal of Civil Engineering and Management, 24(2), 106-115. https://doi.org/10.3846/jcem.2018.458

Li, X., Wu, P., Shen, G. Q., Wang, X., and Teng, Y. (2017). “Mapping the knowledge domains of Building Information Modeling (BIM): A bibliometric approach.” Automation in Construction, 84, 195-206. https://doi.org/10.1016/j.autcon.2017.09.011

Li, X., Li, Z., and Wu, G. (2017). “Modular and offsite construction of piping: Current barriers and route.” Applied Sciences, 7(6), 547. https://doi.org/10.3390/app7060547

Woksepp, S., and Olofsson, T. (2008). “Credibility and applicability of virtual reality models in design and construction.” Advanced Engineering Informatics, 22(4), 520-528. https://doi.org/10.1016/j.aei.2008.06.007

Kim, M., Wang, X., Love, P., Li, H., and Kang, S. C. (2013). “Virtual reality for the built environment: a critical review of recent advances.” Journal of Information Technology in Construction, 18(2013), 279-305.

Marsh, K. L., Wilkie, C. T., Luh, P. B., Zhang, Z., Gifford, T., and Olderman, N. (2014). “Crowd guidance in building emergencies: Using virtual reality experiments to confirm macroscopic mathematical modeling of psychological variables.” Proceedings, Pedestrian and Evacuation Dynamics 2012, pp. 197-212. https://doi.org/fqt4

Kobes, M., Helsloot, I., de Vries, B., and Post, J. (2010). “Exit choice, (pre-)movement time and (pre-)evacuation behaviour in hotel fire evacuation—Behavioural analysis and validation of the use of serious gaming in experimental research.” Procedia Engineering, 3, 37-51. https://doi.org/10.1016/j.proeng.2010.07.006

Kasireddy, V., Zou, Z., Akinci, B., and Rosenberry, J. (2016). “Evaluation and comparison of different virtual reality environments towards supporting tasks done on a virtual construction site.” Proceedings, Construction Research Congress 2016, San Juan, Puerto Rico, May 31–June 2, pp. 2371-2381. https://doi.org/10.1061/9780784479827.236

Du, J., Zou, Z., Shi, Y., and Zhao, D. (2018). “Zero latency: Real-time synchronization of BIM data in virtual reality for collaborative decision-making.” Automation in Construction, 85, 51-64. https://doi.org/10.1016/j.autcon.2017.10.009

Woodhead, R., Stephenson, P., and Morrey, D. (2018). “Digital construction: From point solutions to IoT ecosystem.” Automation in Construction, 93, 35-46. https://doi.org/10.1016/j.autcon.2018.05.004

Ding, Z., Liu, S., Liao, L., and Zhang, L. (2019). “A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects.” Automation in Construction, 102, 45-58. https://doi.org/10.1016/j.autcon.2019.02.012

Feng, H., Yin, C., Li, R., Ma, W., Yu, H., Cao, D., and Zhou, J. (2019). “Flexible virtual fixtures for human-excavator cooperative system.” Automation in Construction, 106, 102897. https://doi.org/10.1016/j.autcon.2019.102897

Heydarian, A., Carneiro, J. P., Gerber, D., Becerik-Gerber, B., Hayes, T., and Wood, W. (2015). “Immersive virtual environments versus physical built environments: A benchmarking study for building design and user-built environment explorations.” Automation in Construction, 54, 116-126. https://doi.org/10.1016/j.autcon.2015.03.020

Kan, C., and Azhar, S. (2016). “Virtual Reality Headsets for Immersive 3D Environment: Investigating Applications in Construction Jobsite Organization.” Proceedings, 20th CIB World Building Congress-Intelligent Built Environment, Tampere, Finland.

Ghimire, R. (2019). “Examining the effectiveness of 4D schedule and virtual reality model on a modular project: UNLV Solar Decathlon Case.” Master’s Thesis, University of Nevada, Las Vegas.

Downloads

Published

2021-01-22

How to Cite

Ghimire, R., Lee, S., Choi, J. O., Lee, J.-Y., & Lee, Y.-C. (2021). Combined Application of 4D BIM Schedule and an Immersive Virtual Reality on a Modular Project: UNLV Solar Decathlon Case. International Journal of Industrialized Construction, 2(1), 1–14. https://doi.org/10.29173/ijic236

Issue

Section

Articles